    DETAILS:

    Block-1 Type-B (North Tower):

    • Structure Work with all Roof Building Design, has been completed.
    • Block Masonry Work has been completed.
    • Electrical Pipe Conduits & Board Fixing Work
    • Internal Plaster Work has been completed.
    • Door Frame Fixing Work has been completed.
    • External Plaster with Scaffolding work is in progress (70% work has been completed).
    • Internal Bathroom Planning With Custom Made Tubs without Tiles has been completed.
    • Plumbing Work (PPRC) has been completed.
    • Plumbing Work (UPVC) is in progress.
    • Electrical Wiring Work is in Progress.

    Block-2 Type-A (South Tower):

    • Structure Work with all Roof Building Design, has been completed.
    • Block Masonry Work has been completed.
    • Electrical Pipe Conduits & Board Fixing Work
    • Internal Plaster Work has been completed.
    • Door Frame Fixing Work has been completed.
    • External Plaster with Scaffolding work is in progress (45% work has been completed).
    • Internal Bathroom Planning With Custom Made Tubs without Tiles has been completed.
    • Plumbing Work (PPRC) has been completed.
    • Plumbing Work (UPVC) is in progress.
    • Electrical Wiring Work is in Progress.

    Note:

    ·  Project Boundary Wall is in Progress.

    ·        R.O. Plant Tank has been completed & Project Tank work is in progress.

   
 

Pictorial View:

 
   
 
   
Copyright © 2006-2007 Lakhani Builders. All Rights Reserved.
All other trademarks and copyrights are the property of their respective holders.
Designed, Hosted & Maintained by Beyond Vision.net